Structural engineering survey of the Parish Hall and Narthex to evaluate potential for future projects.

28 March 2017:  Met with the Engineer and received his drawings.  Essentially, 5 beams of three LVLs each would be required to remove the poles as they support the roof.  Each beam would also require a 16″x4″ column inside the Parish Hall for support in order to not pass through the roof.  These beams will also raise the floor of the attic by 14 inches.  Removing the two walls of the Church Office would require one, perhaps two beams, and not need a corner post.  Finally, the window in the Kitchen can be expanded with simple stud work.

30 March 2017:  Structural Engineering plans are received.

Project Progress

100%

Project Timing

  • Start
    Feb 13 2017
  • End
    Mar 30 2017

02/13/2017 03/30/2017

100%

Overall Project Completion

  • 20%
  • 60%

100%

  • 40%
  • 80%

Establish Coordination 100% Complete

100%
Description
Coordinate site visit for survey

Conduct Site Survey 100% Complete 1/1 Tasks completed

100%
Description
Conduct Site Survey

Generate Documentation 100% Complete

100%
Description
Generate Documentation

Receive Documentation and Recommendations 100% Complete

100%
Description
Receive Documentation and Recommendations