Project Description

This project is to add a 25′ extension onto the east side of the church along the wall of the Parish Hall and Nursery, thereby creating space for a new kitchen and covered patio.  This will then allow direct connection between the two spaces which are currently on opposite sides of the Church.  The design will facilitate large capacity functions, such as Pot Luck Sundays, as well as provide a patio for outside activities.

4 April 2017:  Final design package received.

7 May 2017:  Voter’s Assembly approved construction.

Documents

Project Progress

100%

Overall Project Completion

  • Design Finalized

    Kitchen design finalized

    20%
  • Contractor Bid Accepted

    Contractor Bid Accepted

    60%

100%

  • 40%

    Congregation Approval -- 7 May 2017

    Voter's Assembly to approve the design and procurement of funding.

  • 80%

    Start Construction

    Voter's Assembly to approve the bids and finalize funding.

20%

Design Finalized

Kitchen design finalized

40%

Congregation Approval -- 7 May 2017

Voter's Assembly to approve the design and procurement of funding.

60%

Contractor Bid Accepted

Contractor Bid Accepted

80%

Start Construction

Voter's Assembly to approve the bids and finalize funding.

Floor Plan Design 100% Complete

100%
Description
Floor plan design

Kitchen Design Elements 100% Complete

100%
Description
  • Cabinets
    • Materials
    • Colors
    • Hardware
  • Counter tops
    • Material
    • Color
  • Flooring
    • Material
    • Color

Appliances 55% Complete

55%
Description
  • Additional double stove required
  • Sinks
  • Ice Machine